Turkana Integrated Water Resilience Programme
About this investment 01 · Record
Boreholes, water pans and last-mile reticulation for drought-affected communities across Turkana.
Delivery 02 · Progress
94%
Funds absorption
78%
Results & achievements 03 · Delivery record
What this investment set out to deliver — and how far each measure has come. Overall, 94% of the planned results have been achieved.
Output 1 · Water supply infrastructure constructed and operational
100%Boreholes drilled and equippedboreholesBaseline 0
24 / 24
2021/22 Q1 · 3/32021/22 Q2 · 3/32021/22 Q3 · 3/32021/22 Q4 · 3/32022/23 Q1 · 3/32022/23 Q2 · 3/32022/23 Q3 · 3/32022/23 Q4 · 3/3
Water pans and earth dams rehabilitatedpansBaseline 0
16 / 16
2021/22 Q1 · 2/22021/22 Q2 · 2/22021/22 Q3 · 2/22021/22 Q4 · 2/22022/23 Q1 · 2/22022/23 Q2 · 2/22022/23 Q3 · 2/22022/23 Q4 · 2/2
Output 2 · Communities with sustained access to safe water
88%People with new access to safe waterpeopleBaseline 0
103,200 / 120,000
2021/22 Q1 · 12,900/15,0002021/22 Q2 · 12,900/15,0002021/22 Q3 · 12,900/15,0002021/22 Q4 · 12,900/15,0002022/23 Q1 · 12,900/15,0002022/23 Q2 · 12,900/15,0002022/23 Q3 · 12,900/15,0002022/23 Q4 · 12,900/15,000
Water management committees trainedcommitteesBaseline 0
72 / 80
2021/22 Q1 · 9/102021/22 Q2 · 9/102021/22 Q3 · 9/102021/22 Q4 · 9/102022/23 Q1 · 9/102022/23 Q2 · 9/102022/23 Q3 · 9/102022/23 Q4 · 9/10
Locations 04 · Survey
1 site(s) surveyed for this investment
Partners & funding 05 · Parties
Funders
World BankNational Treasury (GoK)
Implementing partners
NDMAMinistry of Water & Sanitation
Beneficiaries
Pastoralist households