Baringo Community Water Pans
About this investment 01 · Record
Excavation and lining of community water pans with solar pumping.
Delivery 02 · Progress
96%
Funds absorption
88%
Results & achievements 03 · Delivery record
What this investment set out to deliver — and how far each measure has come. Overall, 96% of the planned results have been achieved.
Output 1 · Communities with sustained access to safe water
92%People with new access to safe waterpeopleBaseline 0
112,800 / 120,000
2020/21 Q1 · 14,100/15,0002020/21 Q2 · 14,100/15,0002020/21 Q3 · 14,100/15,0002020/21 Q4 · 14,100/15,0002021/22 Q1 · 14,100/15,0002021/22 Q2 · 14,100/15,0002021/22 Q3 · 14,100/15,0002021/22 Q4 · 14,100/15,000
Water management committees trainedcommitteesBaseline 0
72 / 80
2020/21 Q1 · 9/102020/21 Q2 · 9/102020/21 Q3 · 9/102020/21 Q4 · 9/102021/22 Q1 · 9/102021/22 Q2 · 9/102021/22 Q3 · 9/102021/22 Q4 · 9/10
Output 2 · Water supply infrastructure constructed and operational
100%Boreholes drilled and equippedboreholesBaseline 0
24 / 24
2020/21 Q1 · 3/32020/21 Q2 · 3/32020/21 Q3 · 3/32020/21 Q4 · 3/32021/22 Q1 · 3/32021/22 Q2 · 3/32021/22 Q3 · 3/32021/22 Q4 · 3/3
Water pans and earth dams rehabilitatedpansBaseline 0
16 / 16
2020/21 Q1 · 2/22020/21 Q2 · 2/22020/21 Q3 · 2/22020/21 Q4 · 2/22021/22 Q1 · 2/22021/22 Q2 · 2/22021/22 Q3 · 2/22021/22 Q4 · 2/2
Locations 04 · Survey
1 site(s) surveyed for this investment
Partners & funding 05 · Parties
Funders
National Treasury (GoK)
Implementing partners
Ministry of Water & Sanitation
Beneficiaries
Pastoralist households