Tana River Flood Resilience & Access
About this investment 01 · Record
Flood dykes, raised access roads and early-warning for displaced communities.
Delivery 02 · Progress
55%
Funds absorption
48%
Results & achievements 03 · Delivery record
What this investment set out to deliver — and how far each measure has come. Overall, 55% of the planned results have been achieved.
Output 1 · Community natural-resource management strengthened
56%Community conservancies supportedconservanciesBaseline 0
16 / 24
2022/23 Q1 · 2/32022/23 Q2 · 2/32022/23 Q3 · 2/32022/23 Q4 · 2/32023/24 Q1 · 2/32023/24 Q2 · 2/32023/24 Q3 · 2/32023/24 Q4 · 2/3
Rangeland management plans developedplansBaseline 0
16 / 36
2022/23 Q1 · 2/42022/23 Q2 · 2/42022/23 Q3 · 2/42022/23 Q4 · 2/42023/24 Q1 · 2/42023/24 Q2 · 2/42023/24 Q3 · 2/42023/24 Q4 · 2/4
Output 2 · Degraded landscapes restored
55%Land rehabilitated and reseededhectaresBaseline 0
5,504 / 10,000
2022/23 Q1 · 688/1,2502022/23 Q2 · 688/1,2502022/23 Q3 · 688/1,2502022/23 Q4 · 688/1,2502023/24 Q1 · 688/1,2502023/24 Q2 · 688/1,2502023/24 Q3 · 688/1,2502023/24 Q4 · 688/1,250
Tree seedlings planted and survivingseedlingsBaseline 0
220,000 / 400,000
2022/23 Q1 · 27,500/50,0002022/23 Q2 · 27,500/50,0002022/23 Q3 · 27,500/50,0002022/23 Q4 · 27,500/50,0002023/24 Q1 · 27,500/50,0002023/24 Q2 · 27,500/50,0002023/24 Q3 · 27,500/50,0002023/24 Q4 · 27,500/50,000
Locations 04 · Survey
1 site(s) surveyed for this investment
Partners & funding 05 · Parties
Funders
African Development Bank
Implementing partners
NDMAWorld Vision
Beneficiaries
Internally displaced persons